ROOFERS / GANG - (2 - 4 handed) - Tunbridge Wells (TN1)
DURATION - 12 weeks
Please see below paragraph of the spec and also key meterage’s .
The manufacturer will be DANOSA torch on felt system
START DATE 14th JULY 2025
SPECIFICATION:
Remove the existing aluminium capping and set aside to be reinstated. Prepare the existing roof coverings and leave ready to receive the new waterproofing system. Install a 2-layer high performance waterproofing system. The system will include an underlay and will be finished with a mineralised cap sheet. Form all details and flashings from the same. Cut a chase in the masonry and Install counter flashings formed from a lead replacement material flashing wedged into the chase and point with mastic. Reinstate the salvaged aluminium capping.
PRIME - 2039.84 Sq/Metre
UNDERLAY - 2039.84 Sq/Metre
CAP SHEET - 2039.84 Sq/Metre
KERB + UPSTANDS(200mm high) -448.8 Lm
WELTED DRIP - 243.2 Lm
PIPE PENETRATION 48 Nr
LIFT & RE-FIX ACCESS HATCH 2 Nr
ACCESS HATCH DETAIL 9.4 Lm
PLEASE CONTACT ANDY@ PENTAGON ELITE RESOURCING (07825393857) FOR START DETAILS.
DURATION - 12 weeks
Please see below paragraph of the spec and also key meterage’s .
The manufacturer will be DANOSA torch on felt system
START DATE 14th JULY 2025
SPECIFICATION:
Remove the existing aluminium capping and set aside to be reinstated. Prepare the existing roof coverings and leave ready to receive the new waterproofing system. Install a 2-layer high performance waterproofing system. The system will include an underlay and will be finished with a mineralised cap sheet. Form all details and flashings from the same. Cut a chase in the masonry and Install counter flashings formed from a lead replacement material flashing wedged into the chase and point with mastic. Reinstate the salvaged aluminium capping.
PRIME - 2039.84 Sq/Metre
UNDERLAY - 2039.84 Sq/Metre
CAP SHEET - 2039.84 Sq/Metre
KERB + UPSTANDS(200mm high) -448.8 Lm
WELTED DRIP - 243.2 Lm
PIPE PENETRATION 48 Nr
LIFT & RE-FIX ACCESS HATCH 2 Nr
ACCESS HATCH DETAIL 9.4 Lm